430(16)

Continue with concrete for walks and driveways from Reagan Pkwy to the north end, along the east side of US 42. We will continue to place asphalt drives at the same locations.

We will continue with sewer work on the south end (from Reagan Pkwy to the south end with daily lane closures.

Also we will continue with topsoil on this year’s work areas and raise and adjust of manholes and valve boxes.

 

30412(16)

Harmony: LSM backfill the culvert and prep for roadway placement

Smith Rd.: Continue to remove pavement and prep for the 3 sided box sections